Key Outcomes

  • Total project value: €3 million
  • ​Implementation of biogas plant where no source of existing anaerobic bacteria was available
  • Full operating load being digested into biogas plant
  • Significant reduction in greenhouse gas, odour emissions and solid waste disposal
  • 70% reduction in bunker oil consumption and market exposure

The Challenge

Sustratos De La Ribera is a joint venture between two of the largest slaughterhouses in Costa Rica. Historically, the red meat production plants were not utilising any of their waste.
 
Finn Biogas worked with their client on this missed opportunity to build an on-site biogas plant converting manure, rumen content, fatty waste and blood into biogas which is now used to fire an on-site boiler for rendering operations. 
 
Due to the nature of the existing operations, the biogas plant was in an unusual situation, in that no existing anaerobic bacteria for the seeding and start-up processes was available.  
 
In addition, the fatty waste and highly volatile content of some of the substrates made the start-up highly susceptible to process upset and collapse.  
 
The remote location of the plant meant that spares, modifications and equipment were both expensive and time consuming to access. Local knowledge and capacity to build biogas products were low, which also caused a challenge.


The Solution

Finn Biogas was present on site with their partners AD Solutions (Germany) to provide advice and guidance during the critical stages of plant seeding, heating and start-up of the biogas plant. Given the technical complexity of the commissioning, process critical parameters were monitored daily, and the production was increased to a steady state.   

 


In addition to seeding the digestion, the Finn Biogas team also successfully: 

  • Commissioned gas handling and piping equipment (blowers, flare, analysers, safety valves); 
  • Bump tested motor and sensors;  
  • Tuned pumping and maceration equipment.  

 Have an idea for a biogas project? Get in touch with Finn Biogass.

 
 
 

 

Related Projects

Financial incentives for chiller upgrade Art Gallery of New South Wales

Key outcomes
Energy Conservation’s Measurement and Verification (M&V) and certificate creation services enabled the Art Gallery of New South Wales to achieve:  

  • Funding of over $100,000 through the creation of more than 12,000 Energy Savings Certificates under NSW Energy Savings Scheme (ESS).  
  • Accurate determination of annual savings of 1,200 Megawatt-hoursrepresenting 15% of Gallery consumptionThis equates to annual savings of $140,000 in energy costs and over 1200 tonnes of CO2 equivalent emissions

View Case Study

Evo Energy Turns Heat Green at WhiteWater World

Key Outcomes

  • Reduction in running costs by over 70% 

  • Reduction in carbon emissions by over 35%

Evo Energy installed the largest heat pump system in Australia, with a cutting-edge system upgrade at the popular tourist theme park, WhiteWater World, delivered unparalleled energy efficiencies and helped reduce carbon emissions.

View Case Study

Evo Energy Helps Rivalea to Reduce Environmental Footprint with Custom-Built Biogas Generator

Key Outcomes

  • Generates around 25% of the site’s power per year
  • Offsets over 28,000 per annum tons of CO2 equivalent emissions from grid
  • Methane emissions avoided
  • Energy efficiency of up to 90%

Rivalea, one of Australia’s leading agri-food companies, partnered with Evo Energy minimise their environmental footprint and reduce energy consumption, with the installation of a custom-built biogas generator. 

View Case Study

Cogeneration Heating Aquatic Centre

Key Outcomes
  • $111,000 per year in energy costs
  • 1,224 tonnes in greenhouse gas emissions per year (or the equivalent annual emissions of over 300 cars).
​​Project Summary

The Cardinia Life health and recreational facility was responsible for a largest portion of greenhouse gas emissions in the the Cardinia district (Victoria). Evo Energy Technologies provided a solution which included an update to the facilties while maximumising energy efficiency and achieving cost savings.

View Case Study

Who can accurately measure flow without cutting the pipe? Flowservices can

Key Outcomes 

  • Much higher accuracy and repeatability achieved with non-intrusive clamp-on technology compared to the previously installed open channel meter
  • 3 to 4 times more cost effective than in line flow meter options
  • Maintenance-free with no moving parts or water contact
  • Better measurement performance than the other clamp-on flow meters tested by the customer
  • Ability to offer 80m sensor cable without need of a junction box
  • Great local service and support through Flowservices (FLEXIM distributor)

Business Problem 

MidCoast Water wanted to improve the flow monitoring of water that was pumped from their Bootawa dam to the Bootawa Water Treatment Plant. They engaged Floservices to design a cost-efficient solution in the form of clamp-on ultrasound flow measurement.

View Case Study

Ingham reaps benefits of energy management focus

Key Outcomes 

  • 6% energy savings in 12 months
  • reduced maintenance and labour costs

In just under 12 months, Ingham’s management and operations staff, with guidance from Energetics, collaborated to achieve energy consumption savings across the business of 6% - a significant accomplishment for an energy management program’s first year. 

When compared with resource management programs for similar sized organisations, which typically build up 10% to 15% savings over five to eight years, the result places this iconic poultry producer as a top performer.  

View Case Study

Do you have a smart technology or solution?

Let the business community know about it!

Get in touch