Key outcomes

Energy Conservation’s Measurement and Verification (M&V) and certificate creation services enabled the Art Gallery of New South Wales to achieve:  
  • Funding of over $100,000 through the creation of more than 12,000 Energy Savings Certificates under NSW Energy Savings Scheme (ESS).  
  • Accurate determination of annual savings of 1,200 Megawatt-hoursrepresenting 15% of Gallery consumptionThis equates to annual savings of $140,000 in energy costs and over 1200 tonnes of CO2 equivalent emissions
Learn more about Energy Conservation

Overview

The Art Gallery of NSW is Sydney’s premier art gallery and holds a collection of Australian and international works valued at more than $1 billion.  With a floor area of 25,000 m2 it is one of the largest galleries in Australia, attracting more than a million visitors each year.  A consistent indoor temperature of 22°C±1°C and relative humidity of 55%±5% is required to preserve the Gallery’s irreplaceable collection.  At the heart of the climate control system lies a chilled water system which runs around the clock to provide cooling and dehumidification of the indoor environment 
To ensure ongoing reliability of the chilled water system whilst reducing energy coststhe Gallery replaced two old rotary-screw fluid-chillers with high-efficiency, variable speed, magnetic bearing centrifugal chillers, and introduced further efficiency improvements for the cooling towerswater pumps and control systems.  

The Challenge

To receive financial rewards from the ESS, the energy savings achieved through the project had to be accurately quantified in accordance with the rules of the Scheme using internationally recognised measurement and verification principles.    
The challenge was to design the most accurate but cost-effective method of measuring the performance of the upgraded system against that of the old system, whilst accounting for variations in temperature and humidityEnergy Conservation’s professional certifications and skills in Measurement and Verification (M&V) qualified them as the right company for this complex project.   

The Solution

Energy Conservation examined electricity data, climate data and visitor information and used regression analysis in the development of energy modelsIn addition, they monitored cooling efficiency by measuring chiller energy consumptionchilled water flow and temperatures for comparison of specific chiller performance before and after upgradeEC then applied the International Performance Measurement and Verification Protocol (IPMVP) and successfully verified the accuracy of their energy models and the Gallery’s significant energy savings.  
Energy Conservation’s appointment to the Office of Environment and Heritage’s (OEH) Energy Efficiency Professional Services Panel provided access to government funding for the M&V study. Their accreditation as a certificate provider (ACP) under the ESS using the Project Impact Assessment with Measurement & Verification method enabled them to create and sell Energy Savings Certificates to provide the Gallery with funding to offset the cost of the chilled water system upgrade.  

Testimonial

We tendered for the M and V works through OEH.  Energy Conservations tender response was very good and fully captured the scope of works required.  Energy Conservation were excellent to work with, answered all questions, visited site frequently and provided me constant updates on how the project was tracking.  From day one Energy Conservation instilled confidence and delivered what they promised for this project.  I would recommend EC to anyone seeking similar services”.     
Luke Simkins, Head Building Services, Art Gallery of NSW”  

 
 

 

Related Projects

Evo Energy Turns Heat Green at WhiteWater World

Key Outcomes

  • Reduction in running costs by over 70% 

  • Reduction in carbon emissions by over 35%

Evo Energy installed the largest heat pump system in Australia, with a cutting-edge system upgrade at the popular tourist theme park, WhiteWater World, delivered unparalleled energy efficiencies and helped reduce carbon emissions.

View Case Study

Evo Energy Helps Rivalea to Reduce Environmental Footprint with Custom-Built Biogas Generator

Key Outcomes

  • Generates around 25% of the site’s power per year
  • Offsets over 28,000 per annum tons of CO2 equivalent emissions from grid
  • Methane emissions avoided
  • Energy efficiency of up to 90%

Rivalea, one of Australia’s leading agri-food companies, partnered with Evo Energy minimise their environmental footprint and reduce energy consumption, with the installation of a custom-built biogas generator. 

View Case Study

Cogeneration Heating Aquatic Centre

Key Outcomes
  • $111,000 per year in energy costs
  • 1,224 tonnes in greenhouse gas emissions per year (or the equivalent annual emissions of over 300 cars).
​​Project Summary

The Cardinia Life health and recreational facility was responsible for a largest portion of greenhouse gas emissions in the the Cardinia district (Victoria). Evo Energy Technologies provided a solution which included an update to the facilties while maximumising energy efficiency and achieving cost savings.

View Case Study

Who can accurately measure flow without cutting the pipe? Flowservices can

Key Outcomes 

  • Much higher accuracy and repeatability achieved with non-intrusive clamp-on technology compared to the previously installed open channel meter
  • 3 to 4 times more cost effective than in line flow meter options
  • Maintenance-free with no moving parts or water contact
  • Better measurement performance than the other clamp-on flow meters tested by the customer
  • Ability to offer 80m sensor cable without need of a junction box
  • Great local service and support through Flowservices (FLEXIM distributor)

Business Problem 

MidCoast Water wanted to improve the flow monitoring of water that was pumped from their Bootawa dam to the Bootawa Water Treatment Plant. They engaged Floservices to design a cost-efficient solution in the form of clamp-on ultrasound flow measurement.

View Case Study

Meat Production Turning Waste Into Biogas

Key Outcomes

  • Total project value: €3 million
  • ​Implementation of biogas plant where no source of existing anaerobic bacteria was available
  • Full operating load being digested into biogas plant
  • Significant reduction in greenhouse gas, odour emissions and solid waste disposal
  • 70% reduction in bunker oil consumption and market exposure
The Project

Finn Biogas worked with their client to build an on-site biogas plant converting manure, rumen content, fatty waste and blood into biogas which is now used to fire an on-site boiler for rendering operations. 

 

View Case Study

Ingham reaps benefits of energy management focus

Key Outcomes 

  • 6% energy savings in 12 months
  • reduced maintenance and labour costs

In just under 12 months, Ingham’s management and operations staff, with guidance from Energetics, collaborated to achieve energy consumption savings across the business of 6% - a significant accomplishment for an energy management program’s first year. 

When compared with resource management programs for similar sized organisations, which typically build up 10% to 15% savings over five to eight years, the result places this iconic poultry producer as a top performer.  

View Case Study

Do you have a smart technology or solution?

Let the business community know about it!

Get in touch