Key outcomes

  • Cost savings of $2.7 million per annum

  • Total project value $5.5 million

  • 18 month payback period

  • Saves 5000 tonnes of CO2 per annum
     

ETS Designed and Installed modified exhaust systems to four existing gas generators, utilizing Miratech silencers, to capture enough waste heat for the creation of 5.6MW of additional mine cooling capacity via absorption chillers.
 
In concert with Gordon Brothers Industries, ETS designed and installed the necessary infrastructure to capture the waste heat from existing Third Party owned and operated gas fired generators converting it into 5.6MW of chilled water for use in the mine’s underground mine cooling system. The installation has been operating for close to one year and had an initial payback estimate of just over two years. This has now been revised to 18months and from there will save the mine $2.5M per annum in operation costs and reduce its emissions by 5000 Tonnes of CO2 per year.
 
This unique solution to underground mine cooling meant that the traditional and much more expensive methods of expanding mine cooling capacity were not needed It comprises two 2.7 MW Thermax Absorption Chillers, new cooling water pipework, modified exhaust systems for four of the existing gas engines with new Miratech silencers to divert heat into the absorption Chillers and significant civil infrastructure to house and support the new equipment. Construction commenced in September 2014 and was completed in late January 2015. It was completed on time and on budget with no interruption to mine operations.

 

 

Related Projects

Financial incentives for chiller upgrade Art Gallery of New South Wales

Key outcomes
Energy Conservation’s Measurement and Verification (M&V) and certificate creation services enabled the Art Gallery of New South Wales to achieve:  

  • Funding of over $100,000 through the creation of more than 12,000 Energy Savings Certificates under NSW Energy Savings Scheme (ESS).  
  • Accurate determination of annual savings of 1,200 Megawatt-hoursrepresenting 15% of Gallery consumptionThis equates to annual savings of $140,000 in energy costs and over 1200 tonnes of CO2 equivalent emissions

View Case Study

Evo Energy Turns Heat Green at WhiteWater World

Key Outcomes

  • Reduction in running costs by over 70% 

  • Reduction in carbon emissions by over 35%

Evo Energy installed the largest heat pump system in Australia, with a cutting-edge system upgrade at the popular tourist theme park, WhiteWater World, delivered unparalleled energy efficiencies and helped reduce carbon emissions.

View Case Study

Evo Energy Helps Rivalea to Reduce Environmental Footprint with Custom-Built Biogas Generator

Key Outcomes

  • Generates around 25% of the site’s power per year
  • Offsets over 28,000 per annum tons of CO2 equivalent emissions from grid
  • Methane emissions avoided
  • Energy efficiency of up to 90%

Rivalea, one of Australia’s leading agri-food companies, partnered with Evo Energy minimise their environmental footprint and reduce energy consumption, with the installation of a custom-built biogas generator. 

View Case Study

Cogeneration Heating Aquatic Centre

Key Outcomes
  • $111,000 per year in energy costs
  • 1,224 tonnes in greenhouse gas emissions per year (or the equivalent annual emissions of over 300 cars).
​​Project Summary

The Cardinia Life health and recreational facility was responsible for a largest portion of greenhouse gas emissions in the the Cardinia district (Victoria). Evo Energy Technologies provided a solution which included an update to the facilties while maximumising energy efficiency and achieving cost savings.

View Case Study

Who can accurately measure flow without cutting the pipe? Flowservices can

Key Outcomes 

  • Much higher accuracy and repeatability achieved with non-intrusive clamp-on technology compared to the previously installed open channel meter
  • 3 to 4 times more cost effective than in line flow meter options
  • Maintenance-free with no moving parts or water contact
  • Better measurement performance than the other clamp-on flow meters tested by the customer
  • Ability to offer 80m sensor cable without need of a junction box
  • Great local service and support through Flowservices (FLEXIM distributor)

Business Problem 

MidCoast Water wanted to improve the flow monitoring of water that was pumped from their Bootawa dam to the Bootawa Water Treatment Plant. They engaged Floservices to design a cost-efficient solution in the form of clamp-on ultrasound flow measurement.

View Case Study

Meat Production Turning Waste Into Biogas

Key Outcomes

  • Total project value: €3 million
  • ​Implementation of biogas plant where no source of existing anaerobic bacteria was available
  • Full operating load being digested into biogas plant
  • Significant reduction in greenhouse gas, odour emissions and solid waste disposal
  • 70% reduction in bunker oil consumption and market exposure
The Project

Finn Biogas worked with their client to build an on-site biogas plant converting manure, rumen content, fatty waste and blood into biogas which is now used to fire an on-site boiler for rendering operations. 

 

View Case Study