Key Outcomes

  • $111,000 per year in energy costs
  • 1,224 tonnes in greenhouse gas emissions per year (or the equivalent annual emissions of over 300 cars).

The Challenge

Cardinia Life is the premier health and recreational facility in the Cardinia district of Victoria. The facility was also responsible for a large portion of the district’s greenhouse gas emissions. In 2012 it represented 26% of the council’s emissions or 2,325 tonnes. To mitigate against this, the Cardinia City Council engaged Evo Energy Technologies to provision a cogeneration plant and to upgrade their facilities for maximum energy efficiency and cost savings. 

The Solution

Evo Energy Technologies installed a containerised version of the Miraclegen MC247N-SC CHP unit by mid 2014. This MC247N-SC unit has an electrical output of 135kW and thermal output of 210kW. The stand-alone system was fitted with a Heinzmann Lean Burn Ignition Control for further reductions in energy and emissions. Along with this there was a ComAp IG-NTC-BB controller and IV8 8″ Touch Screen Interface, which was integrated into the facility BMS.
 
Remote monitoring and optimal control was easily achieved via ComAp’s Intellimonitor and Websupervisor systems. This meant the system could be closely monitored from any computer or smartphone device, from anywhere in the world.
header-logo.png

Send an enquiry to EVO Energy Technology.
 

 

Related Projects

Financial incentives for chiller upgrade Art Gallery of New South Wales

Key outcomes
Energy Conservation’s Measurement and Verification (M&V) and certificate creation services enabled the Art Gallery of New South Wales to achieve:  

  • Funding of over $100,000 through the creation of more than 12,000 Energy Savings Certificates under NSW Energy Savings Scheme (ESS).  
  • Accurate determination of annual savings of 1,200 Megawatt-hoursrepresenting 15% of Gallery consumptionThis equates to annual savings of $140,000 in energy costs and over 1200 tonnes of CO2 equivalent emissions

View Case Study

Evo Energy Turns Heat Green at WhiteWater World

Key Outcomes

  • Reduction in running costs by over 70% 

  • Reduction in carbon emissions by over 35%

Evo Energy installed the largest heat pump system in Australia, with a cutting-edge system upgrade at the popular tourist theme park, WhiteWater World, delivered unparalleled energy efficiencies and helped reduce carbon emissions.

View Case Study

Evo Energy Helps Rivalea to Reduce Environmental Footprint with Custom-Built Biogas Generator

Key Outcomes

  • Generates around 25% of the site’s power per year
  • Offsets over 28,000 per annum tons of CO2 equivalent emissions from grid
  • Methane emissions avoided
  • Energy efficiency of up to 90%

Rivalea, one of Australia’s leading agri-food companies, partnered with Evo Energy minimise their environmental footprint and reduce energy consumption, with the installation of a custom-built biogas generator. 

View Case Study

Who can accurately measure flow without cutting the pipe? Flowservices can

Key Outcomes 

  • Much higher accuracy and repeatability achieved with non-intrusive clamp-on technology compared to the previously installed open channel meter
  • 3 to 4 times more cost effective than in line flow meter options
  • Maintenance-free with no moving parts or water contact
  • Better measurement performance than the other clamp-on flow meters tested by the customer
  • Ability to offer 80m sensor cable without need of a junction box
  • Great local service and support through Flowservices (FLEXIM distributor)

Business Problem 

MidCoast Water wanted to improve the flow monitoring of water that was pumped from their Bootawa dam to the Bootawa Water Treatment Plant. They engaged Floservices to design a cost-efficient solution in the form of clamp-on ultrasound flow measurement.

View Case Study

Meat Production Turning Waste Into Biogas

Key Outcomes

  • Total project value: €3 million
  • ā€‹Implementation of biogas plant where no source of existing anaerobic bacteria was available
  • Full operating load being digested into biogas plant
  • Significant reduction in greenhouse gas, odour emissions and solid waste disposal
  • 70% reduction in bunker oil consumption and market exposure
The Project

Finn Biogas worked with their client to build an on-site biogas plant converting manure, rumen content, fatty waste and blood into biogas which is now used to fire an on-site boiler for rendering operations. ā€‹

 

View Case Study

Ingham reaps benefits of energy management focus

Key Outcomes 

  • 6% energy savings in 12 months
  • reduced maintenance and labour costs

In just under 12 months, Ingham’s management and operations staff, with guidance from Energetics, collaborated to achieve energy consumption savings across the business of 6% - a significant accomplishment for an energy management program’s first year. 

When compared with resource management programs for similar sized organisations, which typically build up 10% to 15% savings over five to eight years, the result places this iconic poultry producer as a top performer.  

View Case Study

Could Evo Energy Technologies help save your business time and money?

LET THE BUSINESS COMMUNITY KNOW ABOUT IT!

Send enquiry About Evo Energy Technologies